What should an MEP maintenance tender include?
A full asset register, a clear split between planned preventive maintenance (PPM) and reactive calls, and the SLA you will measure. Without the asset list, bidders price blind and the numbers will not compare.
Group the register by discipline: HVAC (chillers or DX units, AHUs, FCUs, exhaust fans), electrical (MDBs, SMDBs, lighting, earthing), plumbing and drainage (pumps, tanks, water heaters, booster sets) and any life safety interfaces. Give make, model, quantity, location and age where you have it.
- Asset register with quantities per building and floor
- PPM frequencies you expect, or ask bidders to propose them per manufacturer manuals
- Reactive call categories: emergency, urgent, routine
- Spare parts policy: included up to a value cap, or charged at cost plus agreed margin
- Manning: resident technicians, mobile team, or a mix
- CAFM or ticketing system the contractor must use
Which MEP items in a UAE building carry regulatory duties?
Water systems and fire safety systems are the two areas with clear written rules. Put them in the tender as named line items so the bidder prices the compliance work and the certificates.
In Dubai, the Legionella guideline requires water tanks, calorifiers and filters to be cleaned and disinfected at least twice a year, hot water stored at a minimum of 60 °C and delivered to taps at a minimum of 50 °C, and daily records of temperature, pH and chlorine readings. It also asks for a yearly risk assessment and a named trained person responsible for Legionella control.
Fire alarm, firefighting and emergency lighting systems must be maintained by a Civil Defence accredited company. Many owners keep this as a separate specialist contract. State in the tender whether fire systems are in or out of scope, and if they are out, list the interface points the MEP contractor must support (for example, fan shutdown signals, pump room access, DB isolation).
What SLA terms make an MEP contract measurable?
Response and rectification times per priority, PPM completion rate per month, and a reporting format. Write them as numbers you will check, then tie them to a deduction schedule.
- Priority 1 (water leak, power loss, lift trap support): response and make-safe time
- Priority 2 (AC failure in an occupied unit): response and fix time
- Priority 3 (routine defects): scheduled window
- PPM completion target and how missed tasks are carried over
- Monthly report: tickets opened and closed, PPM done, spares used, open risks
- Deduction or credit mechanism for missed KPIs
How do you compare MEP bids fairly?
Give every bidder the same priced schedule: monthly PPM fee per building, call-out rates outside scope, labour rates by trade and a parts markup. Then compare like for like.
Ask for a method statement for each high-risk task (tank cleaning, work at height on rooftop units, live electrical isolation) and a sample PPM checklist for one FCU, one pump set and one DB. The sample tells you more about the bidder's discipline than the cover letter does.
Hold a site visit before the clarification deadline. Plant rooms, roof access and shaft access often change the price.
What does Tamam need to decide whether to bid?
The asset register, site addresses, the term, the start date and the submission deadline. Tamam reviews scope, sites and timing, then tells you whether it will quote.
Availability, scope and commercial terms are confirmed individually for each project. If your prequalification asks for specific licences, approvals or insurance, list them in the invitation and Tamam will reply with what it can provide for that scope.
What to send Tamam with the invitation
- Tender or RFQ documents and any addenda
- Asset register by building, with plant room photos if available
- Site addresses and emirate for each building
- Scope split: PPM, reactive, fire systems in or out, water tank cleaning in or out
- Required SLA and KPI table
- Contract term, start date and site visit date
- Prequalification list and submission deadline
Sources
- Dubai Municipality, Technical Guidelines for Legionella Control in Water System (DM-HSD-GU44-LCWS2, V6, 19 Aug 2025) (checked 2026-11-23)
- Gulf News: Cabinet resolution on civil defence services (No. 24 of 2012), maintenance through accredited companies (checked 2026-11-23)
- Dubai Law No. (6) of 2019 Concerning Ownership of Jointly Owned Real Property (checked 2026-11-23)